A house builder and a
scaffolding company have been fined after two bricklayers were hurt falling
from an unsafe scaffold. Lincoln Magistrates’ Court heard the two men, who have
asked not to be named, were working for Persimmon Homes Ltd on a development
site in Ploughman’s Lane, Bunkers Hill, Lincoln, when the incident happened on
4 April 2012. They were about to start work on a scaffold platform six metres
from the ground, which had been loaded with materials. Just as they started
work, the scaffold collapsed and they fell around two metres on to a platform
below.
One of
the bricklayers, a 62-year-old from Rossington, South Yorkshire, broke his left
foot. He was unable to work for nine weeks. The second, 29, also of Rossington,
bruised his neck and twisted his knee. He missed one day of work.
A Health and Safety Executive
(HSE) investigation found The Cathedral Scaffold Company Ltd had constructed the
scaffold to bridge a narrow gap between the gable ends of two neighbouring
properties. However, the company did not build it to a recognised design, which
would have incorporated standards to transfer loads to the ground. They wrongly
believed they could not fit them and a four board-wide working platform, as
required by Persimmon, into the gap. Instead they used a non-standard
configuration of scaffolding but failed to carry out strength and stability
calculations to ensure it was fit for purpose. The company issued a Handing
Over certificate to Persimmon, setting out restrictions on the use of the
scaffold. This identified it as a general purpose scaffold capable of
supporting a specified distributed weight load, but because no strength or
stability calculations were undertaken by either defendant, this distributed
load could not be guaranteed. Persimmon subsequently overloaded the platform,
causing it to collapse.
HSE
found the weight of just one pack of dry blocks distributed evenly over the
platform would have taken it over the load limit – even without the men, tools
or mortar on the platform. It was likely that the actual loading could have
increased the danger as the blocks were all stacked towards one side of the
platform. Persimmon Homes Ltd, of Fulford, York, pleaded guilty to breaching
Regulation 8(b)(i) of the Work at Height Regulations 2005 and was fined £8,000
and ordered to pay £10,426 costs.
The
Cathedral Scaffold Company Ltd, of Dixon Way, Lincoln, pleaded guilty to
breaching Regulation 8(b)(ii) of the same Regulations and was fined £4,000 with
costs of £5,500.
Speaking
after the hearing, HSE inspector Linda-Jane Rigby said: “Unless a scaffold is a
basic configuration described in recognised guidance it should be designed by
calculation, by a competent person, to ensure it will have adequate strength
and suitability. The design information should describe the sequence and
methods to be adopted when erecting, dismantling and altering the scaffold.
That did not happen in this case. Persimmon accepted handover of the scaffold
and subsequently overloaded it, causing it to collapse.”
No comments:
Post a Comment