Two
brothers have been fined for breaking safety legislation after a contractor
suffered serious brain injuries in a fall while carrying out building work at
one of their farms. The contractor was installing a floor over a slurry lagoon
in a new barn at Gwarllwyn Farm, near Llandysul on 12 June 2012 when the floor
panel he and a workman were standing on gave way, plunging them into the lagoon
four metres below.
The
incident was investigated by the Health and Safety Executive (HSE) which
prosecuted farm owners Andrew Evans and his brother, David Evans, at
Aberystwyth Magistrates Court on Monday 21 July 2014.
The
court heard the contractor was hired to create a cattle shed floor over an
existing slurry lagoon. He erected concrete pillars in the slurry pit then put
pre-formed concrete beams on top and laid concrete wall panels across the beams
instead of panels specifically designed for flooring. These were to hold a
slatted floor and cattle cubicles. As the contractor and another workman were
standing on one of the panels, it gave way, plunging them into the lagoon. The
contractor suffered a head injury and was hospitalised for two month and he is
still undergoing rehabilitation. The workman escaped without injury.
HSE
found the two farmers failed to make a crucial appointment of a construction
and design co-ordinator who would have advised them on their responsibilities
as a construction client and how to ensure the project was managed safely and
without risk to health. The brothers also did not have a principal contractor
so had assumed that role, giving them the responsibility for planning, managing
and monitoring the health and safety aspects of the construction work. However,
no design or construction plans existed and there were no risk assessments or
agreed safe system of work. They also failed to check the contractor was
suitably competent to do the work. The wall panels he used were unsuitable and
the workmen he employed on site had no training or experience in construction.
In addition, the brothers allowed the contractor to use an untrained crane
driver, using a 25 tonne lift capacity crane that had not been thoroughly
tested for ten years, despite this being an annual requirement. They also
failed to supervise or monitor the construction work, which involved a great
deal of working at height, so there were no suitable measures to prevent or
mitigate any effects of a fall.
Andrew
Evans, of Gwarllwyn Farm, Rhydlewis, Llandysul and David Evans of Esgair
Tangwst, Rhydlewis each pleaded guilty to two breaches of the Construction
(Design and Management) Regulations and were each fined a total of £9,000. Each
was ordered to pay costs of £3,560.
HSE
Inspector, Phil Nicolle, speaking after the hearing, said: “Farmers cannot
ignore their legal duties for health and safety when arranging construction
work on their farms. The contractor in this case suffered life-threatening
injuries and has yet to make a full recovery. The Evans brothers were
undertaking a major construction project and failed to make the crucial appointment
of a Construction Design and Management Co-ordinator to advise them on their
responsibilities and how to manage the project safely. They took on the
responsibilities of a principal contractor for planning, managing and
monitoring the health and safety aspects of the construction work, and in all
these respects they failed significantly. If farmers use contractors for any
work they simply cannot tell them what to do and let them get on with it. Both
the client and the contractor have legal duties for health and safety that
can’t be passed to each other by contract. This means they have to work with
each other to make sure the job is done safely. Farmers must always question
their contractors about their health and safety arrangements.”
No comments:
Post a Comment