Three construction companies have been fined after a worker was crushed by a falling section of conveyor at a plant in Sleaford.
The
incident happened during construction of the Sleaford Renewable Energy
plant on Boston Road on 14 February 2013 when the 4.5 tonne conveyor
section overturned during installation.
It trapped Michael Doyle, a
49-year-old employee of Derby-based Shaw Group UK Ltd, who suffered
multiple injuries including four cracked vertebrae, broken ribs, a
punctured lung and broken ankle. He has not returned to work since.
Lincoln
Magistrates’ Court heard yesterday (12 March) that Shaw Group UK Ltd
had been subcontracted to install a boiler and associated equipment ,
including a conveyor system to carry large straw bales, by Burmeister
and Wain Energy (BWE).
BWE was one of two Danish companies, the
other being Burmeister and Wain Scandinavian Contractor (BWSC), that had
formed a consortium to design and build the centre, which burns straw
and wood to create electricity and also to provide heat for some local
authority buildings.
Shaw Group UK Ltd had already lifted three
conveyor sections on to a slope leading up to the boiler by craning them
on to a platform at the bottom of the slope. Skates were bolted to the
front and rear legs which helped keep the section of conveyor on rails
as it was dragged up the slope by manual winches set up at the top.
In
order to fix the sections of conveyor in place workers needed to remove
the skates and used jacks to raise the legs enough to take the skates
off and then lower the legs down onto the rail.
This was carried
out successfully on the first three sections but as the jacks were
released, on the lower legs of the fourth and final section, one side
lowered faster than the other and the conveyor swung towards two workers
before violently swinging the other way and turning on its side,
trapping Mr Doyle, from Fleetwood, Lancashire, underneath.
A Health and Safety Executive (HSE) investigation identified safety failings by all three companies.
Shaw
Group UK Ltd had produced a risk assessment and a plan for the
installation but it did not consider removal of the skates from the legs
of the conveyor sections or the manual winching of the load up the
slope. The document had been sent to BWE for checking but the company
did not pick up on the omission.
The lifting operation using jacks
was not carried out safely and none of the three defendants was
managing or monitoring the work in a way that would ensure its safety.
The
investigation also found that BWSC failed in its responsibility as
principal contractor to ensure work was properly assessed and
co-ordinated between the many contractors on site.
Shaw Group UK
Ltd, of Stores Road, Derby, was fined a total of £17,350 and ordered to
pay costs of £1,710 after pleading guilty to breaching Regulation 3(1)
of the Management of Health and Safety at Work Regulations 1999;
Regulation 8(1)(c) of the Lifting Operations and Lifting Equipment
Regulations 1998; and Regulation 13(2) of the Construction (Design and
Management ) Regulations 2007.
Burmeister and Wain Scandinavian
Contractor, of Gydevang 35, PO Box 235, DK3450, Allerød, Denmark, was
fined £4,670 and ordered to pay costs of £1,710 after pleading guilty to
breaching Section 3(1) of the Health and Safety at Work etc Act 1974.
Burmeister
and Wain Energy, of Luntoftegardsvej 93A, DK 800 Kgs Lyngby, Denmark,
was fined £5,350 and ordered to pay costs of £1,710 after admitting a
breach of Regulation 13(2) of the Construction (Design and Management)
Regulations 2007.
Speaking after the hearing, HSE inspector Martin Giles said:
“This
was a large site with multiple contractors and up to 300 people working
at any one time. Although there was a series of site rules set out in a
construction phase plan, BWSC’s management of the site was poor as each
of the main contractors ran their own areas of the site as they desired
and were able to set additional rules. This led to different procedures
being followed and a lack of control over temporary works.
“The
failure to ensure work was carried out safely on the slope was
symptomatic of more general failures which were the responsibility of
principal contractor BWSC in setting the rules, procedures and checks
needed to manage a large site. These failures put all the workers on
site at risk.
“BWE specified the use of skates for installing the
conveyor system but removing them required adequate risk assessment.
Although the company had read the assessment and method statement
produced by Shaw Group it made no comment on it and did not approve it
before it was implemented. BWE should have picked up on that document’s
failures and asked Shaw Group to re-evaluate before work was allowed to
begin.
“Shaw Group UK Ltd’s risk assessment was flawed, and its
management and monitoring of the task was not sufficient to identify
potential problems and stop the work in the four days before Mr Doyle
was hurt. The actual method of work followed by its employees was unsafe
and led to Mr Doyle’s injuries when the load overturned.”
NEBOSH Combined Construction/General Certificate
No comments:
Post a Comment