A Manchester construction firm has appeared in court over safety
failings after a joiner was badly injured when he fell through a
ceiling. Patrick Moran, 48 from Stretford, had been working on a loft
conversion in Chorlton when the incident happened on 21 May 2013.
Quaintbrook Properties Ltd was prosecuted by the Health and Safety
Executive (HSE) after an investigation found he had been asked to help
install partition walls without any floorboards in place.
Trafford
Magistrates’ Court heard recently (29 August 2014) that the company had
been hired to carry out loft conversions at two neighbouring properties
on York Road. The firm had installed new floor joists but wanted the
partition walls to be fitted before the floorboards, so they could be
easily lifted up in the future. The job sheet instructed the two joiners
to use boards on the site as temporary flooring but when they arrived
they could only find three pieces of wet plywood outside, which were
unusable. They therefore had to use some old loft boards to create
temporary walkways and kept moving them to reach different areas of the
loft. As the joiners were installing the wooden frame for a partition
wall, one of them slipped and his leg went between the floor joists and
through the plasterboard ceiling up to his hip. He managed to pull
himself up onto the joints but suffered severe internal bruising and
continues to suffer from pins and needles to his left hand, caused by
possible nerve damage.
Quaintbrook Properties Ltd, of Oswald Road
in Chorlton, was fined £5,000 and ordered to pay £5,518 in prosecution
costs after pleading guilty to a breach of the Health and Safety at Work
etc Act 1974.
Speaking after the hearing, HSE Inspector Laura
Moran said: “The joiner was badly injured in the incident but it could
easily have been much worse if he had fallen all the way into the room
below. Quaintbrook Properties was responsible for his safety but it
failed to take this responsibility seriously. The company did not give
its employees any information about health and safety, or carry out a
proper assessment of the risks ahead of the work starting. As well as
the missing floorboards, there was also a large opening for the new
staircase without any markings or protective measures around it.
Following the incident, the company arranged for temporary flooring to
be installed across the whole area. If this had been in place at the
time of the incident then the joiner’s injuries could have been
avoided.”
Karen Fryer, Head of Consulting at CRS
said “This is just another example of companies needing proper,
competent health and safety advice. It’s often a RIDDOR-reportable
injury that leads Health and Safety Executive to visit a company. Our SafetyShare
service provides access to a qualified construction health and safety
adviser’s services. As many or as few days service each year as needed –
you simply use as much as you need for a low fixed price”.
No comments:
Post a Comment